SVC reports on the Starline 2500s: We have 13 masters on the way to or already at the factory. Figure 4 more days before they get there, call that 12 May.

Bruce will put some of those into ADB Master Mold 2501. I am not sure how many will fit, maybe eight. He will drive that over to the mold factory on the 13th. It will take about 7 days to get the master mold back, call it the 20th.

Then Bruce will spin the master mold (one day) and sent us samples on the 21st (five days in mail, they arrive the 26th). We will review them (an hour) and notify Bruce which ones are good enough to go into production molds. The production molds for some of the eight(?) will thus be ordered on the 27th, and will take 7 days to get back (3 June). Then a day for production, overnight some samples, two days for a production run (ship the 9th, a week for them to arrive at ADB (16th), a day or two for us to put them on the cart (photos, product descriptions, news releases and promotion). Call it new minis on the cart on or about 18 June. Give or take. I did the same math on the other board 5 minutes ago and got the 12th of June so who knows, somewhere in there.
 
Back
Top